Abstract

Aims: This study illustrates the main factors that influence the cost overruns and schedule delays of tunnel construction megaprojects. Objective: An empirical analysis was carried out based on a dataset collected from a number of recent tunnel megaprojects worldwide. Methods: Analyses of variances and regression analyses were conducted to infer statistical significance and understand the relationships that exist between cost overruns, time delays and variables of context, technical, and governance characteristics of the sample projects. Results: The most significant factors are those related to the complexity of infrastructure and the type of contracting system used to deliver the project. In particular, some technical characteristics pertinent to the size of the tunnel reveal to be influencing factors of both schedule delay and cost overrun, while the usage of a traditional contracting mechanism is likely to impact the cost overrun. The type of infrastructure, region, ownership, and funding scheme are not found to be statistically significant determinants of cost and time performance. Conclusion: This analysis reaffirms that the size and complexity are important factors of typical low performance of tunnel construction megaprojects. The results of this study can be used for strategic design and planning by decision-makers, project managers and designers.

Highlights

  • Megaprojects often fail to meet the predetermined targets of cost and time performance [1 - 3]

  • The type of infrastructure, region, ownership, and funding scheme are not found to be statistically significant determinants of cost and time performance. This analysis reaffirms that the size and complexity are important factors of typical low performance of tunnel construction megaprojects

  • Despite the availability of studies on construction megaprojects and associated cost and schedule performance [9 - 11], little research is available about the cost and schedule performance of tunnel transport megaprojects [12] and the research works that focus on understanding the factors of cost overruns and time delays are just a few [13]

Read more

Summary

Methods

Analyses of variances and regression analyses were conducted to infer statistical significance and understand the relationships that exist between cost overruns, time delays and variables of context, technical, and governance characteristics of the sample projects

Results
Conclusion
INTRODUCTION
Previous Studies
RESEARCH METHODOLOGY
Data Collection and Grouping of Explanatory Variables
Approach for Explanatory Analysis
Descriptive Analysis of Dataset
EXPLANATORY ANALYSIS AND INTERPRETATION OF RESULTS
Influence of Type of Facility
Influence of Region
Trends Over Time
Schedule delay Cost overrun
Influence of Estimated Project Duration and Budget
Influence of Technical Variables
Influence of Ownership
Influence of Financing Mechanism
Influence of Contracting Mechanism
Schedule delay
CONCLUSION