Abstract

Pile cap as an important part used in construction engineering. Construction projects have a completion schedule, and pile caps as part of a construction project must not be delayed. The purpose of this study is to determine the factors that cause delays in Pile cap work. The analysis method to calculate the results of questionnaire distribution is simple correlation analysis. The results of this study indicate that there are seven factors causing delays Pile cap work on the Trans Studio Mall Makassar upgrade project, namely: (1) Lack of manpower, (2) Late delivery of materials, (3) Rainfall intensity factor, (4) Lack of labor expertise, (5) equipment shortage, (6) equipment damage, (7) the factor of the change of design by the owner. From the results of the calculation of the product moment correlation factor of the lack of labor with the Pearson correlation coefficient value of 0.821 has a very strong relationship.

Highlights

  • Secara umum, proyek konstruksi mempunyai rencana jadwal atau waktu dalam melaksanakan proyek yang bertujuan untuk mengatur alokasi sumber daya yang ada

  • The results of this study indicate that there are seven factors causing delays Pile cap work on the Trans Studio Mall Makassar upgrade project, namely: (1) Lack of manpower, (2) Late delivery of materials, (3) Rainfall intensity factor, (4) Lack of labor expertise, (5) equipment shortage, (6) equipment damage, (7) the factor of the change of design by the owner

  • S. Rini, "Faktor-faktor yang Mempengaruhi Keterlambatan Proyek Konstruksi di Surabaya," Jurnal Rekayasa dan Manajemen Konstruksi, vol 6, no., hlm.25-32, 2018

Read more

Summary

Pengumpulan Data

Pengumpulan data pada penelitian ini diperoleh dari data primer dan data sekunder. Data Primer diperoleh dengan melakukan observasi langsung di lapangan, hasil dari wawancara, dan kuesioner. Data sekunder merupakan data yang diperoleh peneliti dari sumber yang ada, data yang diperoleh dapat memberikan tambahan data dan memperkuat data penelitian. Sumber data sekunder yang diperoleh dalam penelitian ini berasal dari time schedule, time schedule digunakan untuk meninjau pelaksanaan pada proyek apakah sesuai dengan waktu yang telah direncanakan

Pengolahan Data
Skala Likert
Analisa Korelasi Sederhana
Analisa Korelasi Sederhana Perhitungan nilai koefisien korelasi