Abstract

We present a project scheduling problem subject to general temporal constraints where the utilization of a set of renewable resources has to be smoothed over time. For solving the NP-hard optimization problem, we point out some important structural properties and introduce a new enumeration scheme. Combining this enumeration scheme with some branch-and-bound techniques, we propose an appropriate solution procedure for the project scheduling problem at hand. To outline the practical importance of resource levelling, we sketch exemplary the optimization of mid-term planning schedules with regard to the resource requirements of IT projects. Finally, we present results from a comprehensive computational study on problem instances of the well-known rlp_j10 and rlp_j20 test sets devised by Kolisch et al. (Benchmark Instances for Project Scheduling Problems, Kluwer, Boston, 1999).

Full Text
Paper version not known

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.