Abstract

The problem considered is the non-preemptive scheduling of independent jobs that consume a resource (which is non-renewable and replenished regularly) on parallel uniformly related machines. The input defines the speed of machines, size of jobs, the quantity of the resource required by the jobs, the replenished quantities, and replenishment dates of the resource. Every job can start processing only after the required quantity of the resource is allocated to the job. The objective function is a generalization of makespan minimization and minimization of the lp-norm of the vector of loads of the machines. We present an EPTAS for this problem. Prior to our work only a PTAS was known in this non-renewable resource settings only for the special case of our problem of makespan minimization on identical machines.

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.