Abstract

The present paper proposes a new methodology to aid the electrification process of local public transport (LPT). In more detail, real drive cycles of traditional buses currently in use are evaluated together with other data to simulate the consumption of equivalent e-buses (electric buses) with similar characteristics. The results are then used in order to design the best charging infrastructure. The proposed methodology is applied to the case study of Algeciras Bay, where a specific line of LPT is considered. Real measurements are used as data for the simulation model, and the average consumption of an equivalent e-bus is obtained for different operating conditions. Based on these results, different sizes and locations for fast-charging infrastructure are proposed, and the size of the depot charging system is defined trying to maintain the current buses timetable. Finally, some future developments of the present work are presented by considering other bus lines that may benefit from the introduction of the defined charging systems.

Highlights

  • With the Paris Agreement in 2015, the members of the UNFCCC agreed to undertake ambitious efforts to keep the global average temperature rise well below 2 ◦ C above preindustrial levels and to strive for an increase of less than 1.5 ◦ C within this century [1].In order to reach this ambitious long-term goal, nations have to take action and drastically reduce their overall carbon dioxide (CO2 ) emissions

  • The adoption of electric buses is currently slow, as depicted in Figure 1, where the electric bus registration in thousands of units is presented for the different regions on the left vertical axis, and the percentage deviation in respect to the previous year for the same regions is reported with straight lines on the right vertical axis

  • In the idea is to use real data coming from actual buses is to use real data coming from actual buses currently currently deployed deployed by by the the public public transport service companies

Read more

Summary

Introduction

With the Paris Agreement in 2015, the members of the UNFCCC agreed to undertake ambitious efforts to keep the global average temperature rise well below 2 ◦ C above preindustrial levels and to strive for an increase of less than 1.5 ◦ C within this century [1]. Real data are collected from traditional internal combustion engine buses that are currently in operation to derive a specific drive cycle that accurately resembles the actual operating conditions to which an equivalent e-bus would be subjected. These data are provided to a simulation tool that evaluates the consumption of the equivalent e-bus.

Methodology
Simulink Simulation Model
Brake System Block
Electric Motor Block
Driveline Block
Motion Equation Block
Battery Block
Battery’s
Case Study Scenario
Bus Data
Considered
Route Characteristics
Line M-120D
Line M-120
Charging System
Opportunity Charging
15. Timetables
Two Opportunity Chargers of 300 kW
16. SOC buses with one one
Depot Charging
Future Expansion
Full Text
Paper version not known

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.