Abstract

For the formation of programs for housing construction and planning of capital investments, when developing the strategic planning companies by construction companies, the norms or calculated indicators of the duration of the construction of high-rise residential buildings and multifunctional complexes are mandatory. Determination of stable values of the parameters for the high-rise construction residential buildings provides an opportunity to establish a reasonable duration of construction at the planning and design stages of residential complexes, taking into account the influence of market conditions factors. The concept of the formation of enlarged models for the high-rise construction residential buildings is based on a real mapping in time and space of the most significant redistribution with their organizational and technological interconnection - the preparatory period, the underground part, the above-ground part, external engineering networks, landscaping. The total duration of the construction of a residential building, depending on the duration of each redistribution and the degree of their overlapping, can be determined by one of the proposed four options. At the same time, a unified approach to determining the overall duration of construction on the basis of the provisions of a streamlined construction organization with the testing of results on the example of high-rise residential buildings of the typical I-155B series was developed, and the coefficients for combining the work and the main redevelopment of the building were determined.

Highlights

  • In Russia, the practice of multi-storey mass housing construction and design standards was previously focused on the height of buildings up to 75 m

  • In works [1, 2], the authors consider the trends in the development of high-rise construction in Russia

  • For example, for residential buildings I-155B the coefficients of combination of works during the device of technical underground vary in the range from 0.17 to 0.50 with the duration of erection of the underground part from 52.9 days. up to 76.5 days, and when erecting the above-ground part, the coefficients of work combination vary from 0.09 to 0.67 with the duration of this redistribution from 265.5 days. up to 393.2 days

Read more

Summary

Introduction

In Russia, the practice of multi-storey mass housing construction and design standards was previously focused on the height of buildings up to 75 m. High-rise buildings are considered to be above 75 m. According to the number of floors, the existing classifications are rather conventional. Residential buildings are considered high-rise if there are at least 25 floors. In works [1, 2], the authors consider the trends in the development of high-rise construction in Russia. In works [3,4,5], the authors study the international experience of high-

Objectives
Methods
Results
Conclusion