Abstract

The Cheung Chau submarine pipeline between Hong Kong’s Lantau and Cheung Chau islands is a 1·4 km long, 500 mm diameter water main installed by horizontal directional drilling. It is one of the largest trenchless pipeline projects undertaken in Hong Kong. Drilling through a variety of rock strata up to 100 m below sea level was inherently risky, so use of an appropriate procurement strategy was pivotal to controlling costs and ensuring successful delivery. The government’s Water Supplies Department opted to adopt the Institution of Civil Engineers’ NEC3 Engineering and Construction Contract for the project. This paper describes the scope of the work, how an appropriate contract strategy was chosen and how NEC3 facilitated effective risk management during construction. It concludes with a recommendation that NEC3 brings valuable benefits and is suitable for use in future similar projects.

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.