Abstract

A new calculation procedure, called PACT, is presented for the probabilistic analysis of the construction times and costs of tunneling. Once the tunnel strength is divided into homogeneous sections, it is necessary that all the operations on the critical path and the quantities of materials used for each of the previously identified classes are described in analytical terms. A selection is made from the parameters that show a certain degree of uncertainty. A standard deviation of the probabilistic distribution is defined for these parameters. The final result is the identification of the probability ellipses with a certain degree of reliability. The ellipses define the total field of variability of the construction times and costs of the tunneling. The procedure was successfully applied to the pilot tunnel of the Italian section of a 13-km long alpine tunnel. It proved possible to obtain the joined probabilistic description of the times and costs as a result of the evaluation of 95 elementary parameters, 25 of which are considered probabilistic ones because of the uncertainties of their estimation.

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.