Abstract

Cost overrun is a serious issue in the construction industry worldwide, including Pakistan. Cost overrun is a critical and serious issue found in highway projects among all construction projects in Pakistan. Cost overrun occurs when the final cost of the projects exceeds the actual cost of the project. The main objective of this research is to identify the main causes of cost overrun and to determine possible mitigation measures of the identified main causes of cost overrun from contractors of highway/road projects of Pakistan. In this study, a mixed mode (quantitative and qualitative) approach was used. A deep literature review helped to identify the 30 most common causes of cost overrun in the construction industry. In the first stage, a questionnaire was developed, and a survey was carried out among professional and experts who were working with contractors in highway projects. In the second stage, a semi-structured questionnaire was developed, and a survey was carried out to determine the possible mitigation measures of the identified main causes of cost overrun. Collected data for the first stage from experts were inserted in SPSS and were analyzed by using the average index method and the data of the second stage were analyzed by content analysis. It is expected that the findings of this research will be useful and helpful for the construction stakeholders to control and mitigate the major causes of cost overrun.

Highlights

  • The construction industry is known as a major source of economic growth of any country [1]

  • There is a need to explore the major causes of cost overrun in highway projects and determine ways to cope with the problem

  • A thorough literature review was conducted, and a questionnaire was designed consisting of 30 main causes identified from previous studies

Read more

Summary

Introduction

The construction industry is known as a major source of economic growth of any country [1]. The construction industry is known as a complex in nature and fragmented industry, it is facing critical problems of cost overrun, low quality, time overrun, construction waste, low productivity, etc. Out of these problems, cost overrun is one of the major ones as money is always of high importance [3, 4]. In Qatar construction industry more than 50% of construction projects faced serious issues of cost overrun [7, 8]. According to [12], cost overrun is more than 100% of the total cost of a project in both developed and developing countries

Objectives
Methods
Results
Conclusion

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.