Abstract

The small hydropower stations on most tributaries in the middle reaches of Salween River are mostly high-head diversion hydropower stations, and the choice of hub arrangement scheme is an important content of the preliminary construction project. Taking Yamu River-I Hydropower Station as an example, this paper compares and analyzes the layout scheme of the main hub of the project from the aspects of dam site, dam type, regulation scheme, diversion route and site selection, and summarizes the optimization ideas and characteristics of the layout scheme of the main hub of the project, so as to be helpful for the preliminary design of similar hydropower stations.