Abstract

Background: Nowadays, the construction of urban tunnels for rapid transportation in metropolises is necessary. Since these tunnels are excavated at low depths, they are often associated with different problems and hazards. Some of them can reduce the efficiency of the tunnel boring machines and sometimes will stop the project. Among these problems the clogging can cause problems at the cutter head, in the chamber, and in other sections where the material transference occurs. Objective: The main purpose of this paper is to evaluate and determine the risk of clogging in the tunneling boring machine in Line 6 of the Tehran Metro. It includes stations: Amirkabir, Shohada Square, Emam Hossein Square and Sayyadeh Shirazi. This phenomenon induces an adhesion of the shield with the soil, increasing the necessary shear forces and it can eventually leads to the project interruption. Methods: Due to the fact that the criterion for the behavior of fine soils against moisture is Atterberg Limits, therefore, Atterberg Limits and the water content were utilized. For this purpose, the new method proposed by Hollman and Thewes (2013) was used. In this study, in addition to the Atterberg limits, the amount of free water resulting from the machine and from the underground water inflow was included in the calculations. Results: It was found that the water content should be increased carefully as the soil is very sensitive to this parameter. An increase of 15% of the water content permits to reduce the risk of clogging. If the added free water amount 15%, the probability of clogging becomes high. Whereas, in case where the added free water amount reaches 20%, the risk of clogging decreases significantly. Conclusion: According to the performed assessments, it was found that critical areas for the clogging aspect are both the cutter head and the chamber. The sensitivity of the soil is very important to the free water amount. Therefore, due to the behavior of sticky and plastic of clay soils against increasing water, it is necessary to determine the percentage of allowable water used in mechanized excavation projects.

Highlights

  • Tunnel Boring Machines (TBM) permit to increase the excavation speed and decrease the ground displacement

  • In addition to the Atterberg limits, the amount of free water resulting from the machine and from the underground water inflow was included in the calculations

  • It was found that the water content should be increased carefully as the soil is very sensitive to this parameter

Read more

Summary

Objective

The main purpose of this paper is to evaluate and determine the risk of clogging in the tunneling boring machine in Line 6 of the Tehran Metro. It includes stations: Amirkabir, Shohada Square, Emam Hossein Square and Sayyadeh Shirazi. This phenomenon induces an adhesion of the shield with the soil, increasing the necessary shear forces and it can eventually leads to the project interruption

Methods
Results
Conclusion
INTRODUCTION
IMPACTS OF CLOGGING ON TUNNELING
Tehran Subway Line 6
Engineering Geology
Plasticity and Consistency
Free Water Content
Development of the Basic form of the Diagram
OF THE RESULTS
CONCLUSION

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.