Abstract

Gaoshiti-Moxi structure belt of An-Yue Sinian gas reservoir, which was China’s largest monomer Marine carbonate gas reservoir up to now, located in vying-dragon female temple structure group that belong to the ancient uplift slope of the middle of Sichuan. With the exploration and development of high temperature and high pressure carbonate reservoir, a large number of challenges and problems, such as long isolation section, active oil-gas show, large temperature difference, prone to super retarding cement slurry and gas channeling at flare position, have been encountered in the cementing of 177.8 mm hang-liner. In order to solve these problems, numerous measures and methods have been put into use for reducing the safety risk of cementing and improving cementing quality. The large temperature difference channeling cement slurry system, effective anti-pollution spacer and high-pressure packer type liner hanger were developed and applied for field tests in the early stage of development. In addition, equilibrium pressure cementing technology, optimizing of centralizer placement and plasma column structure, improvement of pump displacement and hold pressure while waiting on cement were used to ensure nice displacement efficiency and cementing quality. As Moxi X well for example, the cementing quality factor of merit was 40.29% and the qualification rate was up to 78.87% after adopting the cementing measures and methods above. The cementing quality was much higher than previous level and provided technical support for Gaoshiti-Moxi area.

Highlights

  • Gaoshiti-Moxi structure belt of An-Yue Sinian gas reservoir, which was China’s largest monomer Marine carbonate gas reservoir up to now, located in vying-dragon female temple structure group that belong to the ancient uplift slope of the middle of Sichuan

  • It is confronted with long cementing section, large temperature difference, and easy to occur extra retarded set in the liner cementing of the deep well in Gaoshiti-Moxi area

  • Since 2012, counter pressure cementing, build the pressure while waiting on cement, high density anti channeling cement slurry system and packer type liner hanger were used as the main body agent technology of the hanging anti-gas channeling liner cementing technique

Read more

Summary

Introduction

Gaoshiti-Moxi structure belt of An-Yue Sinian gas reservoir, which was China’s largest monomer Marine carbonate gas reservoir up to now, located in vying-dragon female temple structure group that belong to the ancient uplift slope of the middle of Sichuan. It was designed to Jialing river, Changxing, Maokou and other relative high pressure layer formations As a result, it is confronted with long cementing section, large temperature difference, and easy to occur extra retarded set in the liner cementing of the deep well in Gaoshiti-Moxi area. The microannulus was directly caused by casing radial shrinkage which was indirectly on account of greatly reduced drilling fluid density. Problems mentioned above, such as the temperature rise of the upper wellbore, the decline strength of the cement ring, can lead to many challenges and difficulties in the later stage [3]. It can meet the needs of follow-up operations for cementing the integrity of the wellbore

Challenges of Cementing
Methods for Improving Cementing Quality
Matching Technology for Cementing
Analysis of Field Application
Findings
Conclusions