Background: The accuracy of the cost estimate is a key success factor for any construction project. It is the base for an effective tendering process. It can also be considered as the cornerstone of the cost control process. Objective: This paper aims to develop a model that can be used to assess the expected cost estimating accuracy of construction projects. This model is named as Construction Cost Estimate Accuracy Index (CCEAI). Methods: A questionnaire survey that contains fifteen factors clustered into four categories was carried out among 90 experts based on the construction cost estimate. Only sixty-six questionnaires were returned. The Analytical Hierarchy Process (AHP) was used to identify the relative weights of the different cost estimates. Results: The questionnaire results were analyzed using the AHP technique to calculate the relative weight for each of the input factors and categories. A Construction Cost Estimating Accuracy Assessment model (CCEAI) was developed based on the calculated relative weights. Then, three projects were used as case study applications to check the validity of the proposed model. The results showed that the CCEAI model is greatly reliable in predicting the expected accuracy of the cost estimate. Conclusion: The results of this research and the developed model are very important and can be considered as a powerful tool to predict and improve the expected accuracy of any future construction cost estimate.

Highlights

  • MethodsA questionnaire survey that contains fifteen factors clustered into four categories was carried out among 90 experts based on the construction cost estimate

  • The construction industry contributes significantly to global economic development [1] and the cost estimate is the most vital step involved [1, 2]

  • A questionnaire survey that contains fifteen factors clustered into four categories was carried out among 90 experts based on the construction cost estimate

Read more

Summary

Methods

A questionnaire survey that contains fifteen factors clustered into four categories was carried out among 90 experts based on the construction cost estimate. The Analytical Hierarchy Process (AHP) was used to identify the relative weights of the different cost estimates

Results
Conclusion
INTRODUCTION
Factors Affecting the Accuracy of Construction Cost Estimate
Cost Modeling
THE RESEARCH OBJECTIVES
RESEARCH METHODOLOGY
Analytical Hierarchy Process
AHP Results
Model Development
Cost Performance Scale
The Validity of the Model
Contractor characteristics
Case Studies
CONCLUSION

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.