Abstract
This paper presents a methodology for analyzing engineering-related delays in construction projects using Quality Function Deployment (QFD). The steps of the QFD technique are combined in the quality and control policy. A reference matrix based on the literature review is constructed with engineering delays and a survey of all parties involved in construction projects. The QFD matrix aids in identifying the most significant reasons for delays and claims in the construction projects. For the identified reasons, solutions have been developed to limit or reduce them. The mean sources of construction delays include engineering, construction, financial/economic, management/administrative, and force majeure. This paper presents a knowledge-based QFD technique dedicated to engineering-related delays. Three categories of Engineering-related delays are considered in the proposed system. These categories are 1) design development, 2) workshop drawings, and 3) project party’s changes delays. The knowledge of the QFD matrix is acquired from literature, Federation International des Ingenious - Conseils (FIDIC) contract forms, domain experts, as well as a questionnaire survey. Three classes of participants (i.e., consultants, contractors, and Employers) have been approached to get their feedback on the cases of engineering-related delays. The proposed approach helps to limit or reduce delays in construction projects caused by the engineer. Accordingly, it was concluded to the most important reasons that led to the delay of construction projects related to the engineer, using QFD.
Highlights
The construction industry has different characteristics that may lead to delays, which might lead to disputes between the various parties of the project
At the intersection for each technical requirement (TR) and Engineering-Related Delays (ERD), the correlation is evaluated according to three weights
For each TR, the total weighted correlation is calculated as the sum of products of stakeholder importance and its correlation weight
Summary
The construction industry has different characteristics that may lead to delays, which might lead to disputes between the various parties of the project. The flexibility of owners to make changes during the execution phase, the distribution of risks between owners and contractors, and the degree of owner’s involvement in the project control during construction time may vary from a procurement strategy to another. Owners used to transfer the major risks to contractors. These risks include; inflation, accidents, low labor productivity, adverse weather, shortage of materials and skilled labor, and unforeseen site conditions. Delays and claims have become a repetitive phenomenon in the construction industry. Such a phenomenon, if not managed efficiently, would hinder the success of many construction projects, and slow down the wheel of development
Talk to us
Join us for a 30 min session where you can share your feedback and ask us any queries you have
Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.