Abstract
Purpose: The purpose of this study was to determine the maintenance intervals of critical components of jet dyeing machines in an effort to minimize downtime and calculate maintenance costs for engine damage to the jet dyeing. Design/ methodology/ approach: In this study an optimization method was developed to determine the replacement interval of a critical component, namely the Age Replacement Method. Findings: Based on the results of the calculation interval obtained preventive care critical components of jet engines during dyeing 1549 hours. It means that the component must be replaced before operation for 1549 hours or there is 6 times the turnover of prevention under taken in the interval of one year and the resulting decrease in the total cost of 82%. Research limitations/ implications: A review conducted in this paper against one component only, and then it can be developed for this type of component production machines. Practical implications: If the company is implementing a policy of replacement of critical components of the engine on the jet dyeing machine with a method of age replacement, then it will occur treatment cost savings amounting to Rp. 6,752,886 lower when compared with the initial conditions the company previously Rp 37,441,132. Originality/ value: This study combines the Pareto Diagram method and the Age Replacement Method to obtain optimum maintenance scheduling.
Highlights
Problem while many production process hampered by the frequent stop of the engine because the jet dyeing machine damage
In this study the methodology is determining the evaluation of the current treatment system, problem analysis, identifying the time between damage, determining the timetable, the proposed time interval improvement critical components of the Dyeing Machine, Analysis, Conclusions and Suggestions
Downtime Jet Dyeing Data The observations were made on machines that experienced the greatest total damage downtime, namely the Jet Dyeing engine Determining the critical components of the Jet Dyeing engine as seen in Fig. 5: Figure 5
Summary
The purpose of this study was to determine the maintenance intervals of critical components of jet dyeing machines in an effort to minimize downtime and calculate maintenance costs for engine damage to the jet dyeing
Talk to us
Join us for a 30 min session where you can share your feedback and ask us any queries you have
Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.