Abstract

Very Fast Transients (VFT) originate mainly from disconnector switching operations in Gas Insulated Substations (GIS). In order to determine the rate-of-rise of Very Fast Transient Overvoltage (VFTO) in a 550 kV GIS, simulations are carried out using EMTP-RV. Each component of the GIS is modeled by distributed line model and lumped model based on equivalent circuits. The various switching conditions according to closing point-on-wave and trapped charge are simulated, and the results are analyzed. Also, the analysis of travelling wave using a lattice diagram is conducted to verify the simulation results.