Abstract

The excavation of connected aisle is one of the key risks for the construction of subway in the coastal soft clay layer. The excavation of sump-pit will adversely affect the deformation of the ground and connected aisle, increase the risk of the project. The finite element software ABAQUS is used to carry out numerical simulation research on the excavation of sump-pit. The influence of deformation of ground and connected aisle were analyzed by the method of changing the position of sump-pit excavation. The result showed that: the most significant influence of sump-pit excavation was crown settlement, the second important influence was ground settlement, and the influence of headroom convergence was slight. The maximum ground settlement increased by 7% and the maximum crown settlement by 13% if the sump-pit was built in the middle of connected aisle.