Abstract
PT Asia Sealand Engineering is a company engaged in offshore industry services. This study aims to profit. (EVM). The EVM concept of the three indicators is the Work Schedule Budget (BCWS), Work Performance Cost Budget (BCWP) and Actual Cost of Work Performance (ACWP). From these indicators are then analyzed to Cost Variance (CV), Cost Performance Index (CPI), Variance Schedule (SV) and Index Performance Schedule (SPI). After these talent indexes can be calculated Estimate at Completion (EAC), Estimate to Complete (ETC) and Time Estimate (TE). The project under study is project "Y" module 301 train 3, bacth 5 with job specification in Structure section. The results show that the project cost overrun and sechedule overrun. This means focusing the project down. Estimated cost of project lit (ETC) is Rp. 710.980.113.00. Total total cost can be seen from the calculation of EAC is Rp. 7.595.984.113, - and the estimated time to generate TE is 302 days.
Highlights
Abstrak PT Asian Sealand Engineering merupakan perusahaan yang bergerak dibidang jasa industri offshore
1) Program Studi Administrasi Bisnis Politeknik Negeri Bengkalis,email: elviwahyuni09@gmail.com 2) Program Studi Administrasi Bisnis Politeknik Negeri Bengkalis,email: benk@polibatam.ac.id abtsract PT Asia Sealand Engineering is a company engaged in offshore industry services
The Earned Value Management (EVM) concept of the three indicators is the Work Schedule Budget (BCWS), Work Performance Cost Budget (BCWP) and Actual Cost of Work Performance (ACWP). From these indicators are analyzed to Cost Variance (CV), Cost Performance Index (CPI), Variance Schedule (SV) and Index Performance Schedule (SPI)
Summary
Berdasarkan pada rumusan masalah yang telah dikemukakan, maka tujuan dilaksanakannya penelitian ini adalah untuk mengetahui bagaimana penerapan EVM (Earned Value Management) dalam menilai kinerja proyek Yamal LNG, a. Untuk mengetahui apakah kinerja proyek berdasarkan waktu pelaksanaan proyek sesuai dengan rencana awal proyek b. Untuk mengetahui apakah kinerja proyek berdasarkan biaya pelaksanaan proyek sesuai dengan rencana awal proyek c. Untuk mengetahui estimasi biaya dan waktu yang dibutuhkan untuk menyelesaikan proyek