Abstract
The time, quality, and cost are three important but contradictive objectives in a building construction project. It is a tough challenge for project managers to optimize them since they are different parameters. This paper presents a time-cost-quality optimization model that enables managers to optimize multiobjectives. The model is from the project breakdown structure method where task resources in a construction project are divided into a series of activities and further into construction labors, materials, equipment, and administration. The resources utilized in a construction activity would eventually determine its construction time, cost, and quality, and a complex time-cost-quality trade-off model is finally generated based on correlations between construction activities. A genetic algorithm tool is applied in the model to solve the comprehensive nonlinear time-cost-quality problems. Building of a three-storey house is an example to illustrate the implementation of the model, demonstrate its advantages in optimizing trade-off of construction time, cost, and quality, and help make a winning decision in construction practices. The computational time-cost-quality curves in visual graphics from the case study prove traditional cost-time assumptions reasonable and also prove this time-cost-quality trade-off model sophisticated.
Highlights
The time, quality, and cost are usually three contradictive objectives which are often traded off in project practices by managers randomly if they lack efficient tools
El-Rayes and Kandil [11] presented a multiobjective model to search for an optimal resource utilization plan that minimizes construction cost and time while maximizing its quality, applied genetic algorithm to provide the capability of quantifying and considering quality, and visualized optimal tradeoffs among construction time, cost, and quality by an application example
When labors are working together as a construction crew in a construction activity (i), their working duration is the time of the construction activity, which could be estimated by the construction quantities (QNT) and the actual productivity, overtime factors: DUR(i)
Summary
The time, quality, and cost are usually three contradictive objectives which are often traded off in project practices by managers randomly if they lack efficient tools. Geem [7] employed the harmony search algorithm to perform timecost biobjective tradeoff where a network of up to 18 nodes was tested well These new paradigm algorithms were able to obtain optimal solutions for cost-time tradeoff models within only moderate computational effort. Quality is an important parameter correlating highly with time and cost parameters It is not a quantitative parameter in nature, practical time-cost-quality tradeoff models are seldom developed from previous research works of the literature. El-Rayes and Kandil [11] presented a multiobjective model to search for an optimal resource utilization plan that minimizes construction cost and time while maximizing its quality, applied genetic algorithm to provide the capability of quantifying and considering quality, and visualized optimal tradeoffs among construction time, cost, and quality by an application example. This paper will present a new solution for solving time-cost-quality tradeoff problem based on project breakdown structure method and task resource allocation
Talk to us
Join us for a 30 min session where you can share your feedback and ask us any queries you have
Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.