Abstract

The purpose of this research is to develop a new procedure for generating a proactive baseline schedule for the resource constrained project scheduling problem. The main advantage of this new procedure is that it is completely independent of the reactive policy applied. This contrasts with the traditional methods that assume a predefined reactive policy. First, we define a new robustness measure, then we introduce a branch-and-cut method for solving a sample average approximation of our original problem. In a computational experiment, we show that our procedure outperforms two other published methods, assuming different robustness measures.