Abstract

In this paper a recursive method of determining the exact probability distribution of the project completion time in stochastic PERT networks is presented. It is assumed that durations of particular tasks are independent random variables with known distributions. The method concerns any network and can be applied in the case of any continuous distributions of task durations. Examples of exact density functions of project completion time for some networks are given. A comparison with the straightforward method is also included.

Full Text
Paper version not known

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.