Abstract
The objective of this research was to schedule project activities based on maximum net present value (NPV) and minimum duration. A new hybrid heuristic based on the combination of minimum late start (MLS) and shortest processing time (SPT) priority-rules heuristics was developed. The new late start and shortest processing time (LSSPT) heuristic was tested using 60 problems of the Patterson set, and results compared with 4 other heuristics. To test all 5 previous heuristics, 5 computer programs were developed. Statistical analysis was performed. Results indicate that the new heuristic produced better and encouraging results.
Talk to us
Join us for a 30 min session where you can share your feedback and ask us any queries you have
Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.