Abstract
Battery energy storage systems (BESSs) are gaining increasing importance in the low carbon transformation of power systems. Their deployment in the power grid, however, is currently challenged by the economic viability of BESS projects. To drive the growth of the BESS industry, private, commercial, and institutional investments in large-scale BESS projects are needed. For financiers and investors, choosing an appropriate BESS installation location is a crucial task that requires important considerations. However, so far, studies targeting the BESS placement problem have mainly focused on minimizing operational losses, solving power quality issues, and improving the voltage profile of the system. Implementing such approaches only considers the operational feasibility of BESS at the installation site while ignoring its business feasibility. Therefore, in this paper, we approach the BESS placement problem from a business viewpoint by conducting a stage-level investigation of BESS projects. First, we identify the factors impacting the business feasibility of placement decisions in projects’ construction, connection, operation, and disposal stages and propose cost and time effective measures for making them business friendly. We investigate several factors such as profitability of grid services, integrability of renewable resources, affordability of connection charges, and the usability of BESS capacity. Second, we investigate the business potential of placing BESSs in different grid-levels of the power system and examine BESS connection procedures at those levels. Third, we implement the proposed approach for installing a BESS in the Danish island of Bornholm, for which, we investigate multiple locations of the Bornholm power system.
Highlights
Rising environmental concerns and higher climate change awareness is increasing reliance on renewable energy sources (RES) in the elec tricity sector
This paper identifies limitations in current Battery energy storage systems (BESSs) placement ap proaches and investigates how a business-oriented approach can be applied in different stages and voltage levels of BESS projects to over come these limitations
To do that we investigated business requirements of placement decisions taken in distinct stages of BESS projects
Summary
Rising environmental concerns and higher climate change awareness is increasing reliance on renewable energy sources (RES) in the elec tricity sector. Numerous studies have investigated BESS placement in power systems In these studies, factors like system losses, voltage stability, and power quality have mainly been considered, as recognized in a recent review survey [2]. A few studies have considered operational costs while investigating BESS placement They have either ach ieved reduced costs by minimizing energy losses [22,23,24] or achieved energy savings by improving voltage stability [25]. Placement decisions impacting the BESS pro jects over their lifetime are discussed in detail This is achieved by considering the business feasibility of various stages of BESS projects. The busi ness potential of placing BESSs in different voltage levels of the power network is investigated This is achieved by considering BESS services and BESS connection charges at the high voltage (HV), medium voltage.
Talk to us
Join us for a 30 min session where you can share your feedback and ask us any queries you have