Abstract

In densely built urban areas, it is inevitable that tunnels will be constructed near existing pile groups. The bearing capacity of a pile group depends on shear stress along the soil-pile interface and normal stress underneath the pile toe while the two would be adversely affected by the unloading process of tunneling. Although extensive studies have been conducted to investigate the effects of tunnel construction on existing single piles, the influence of twin tunnel advancement on an existing pile group is merely reported in the literature. In this study, a series of three-dimensional centrifuge tests were carried out to investigate the response of an existing pile group under working load subjected to twin tunneling at various locations in dry Toyoura sand. In each twin tunneling test, the first tunnel is constructed near the mid-depth of the pile shaft, while the second tunnel is subsequently constructed either next to, below or right underneath the pile toe (Tests G_ST, G_SB and G_SU, respectively). Among the three tests, the 2nd tunnel excavated near the pile toe (Test G_ST) results in the smallest settlement but the largest transverse tilting (0.2%) of pile group. Significant bending moment was induced at the pile head (1.4 times of its bending moment capacity) due to the 2nd tunnel T. On the contrary, tunneling right underneath the toe of pile (i.e., Test G_SU) results in the smallest tilting but largest settlement of the pile group (4.6% of pile diameter) and incremental mobilisation of shaft resistance (13%). Due to stress release by the twin tunneling, the axial force taken by the front piles close to tunnels was reduced and partially transferred to the rear piles. This load transfer can increase the axial force in rear piles by 24%.

Highlights

  • Due to land shortage, high-rise buildings are preferred to meet the development and economical growth in major cities

  • The largest Sp is caused by tunneling right underneath the pile. This is because tunneling right underneath the pile group resulted in the largest reduction of toe resistance of all four piles

  • Axial load acting on the pile group transferred to the lower half of front pile P1 shaft and to its adjacent rear pile P2 to maintain equilibrium

Read more

Summary

INTRODUCTION

High-rise buildings are preferred to meet the development and economical growth in major cities. Speaking, tunneling adjacent to existing pile foundations, results in substantial changes in the axial load of piles and in pile settlement. Both are found to heavily depend on tunnel location in relation to the pile. Authors in [18] carried out two centrifuge tests to investigate influence of construction sequences of twin tunneling on an existing single pile in medium dense dry sand. To investigate responses of pile group subjected to twin tunneling at various locations, a series of centrifuge were carried out in this study. Measurements in the centrifuge tests include settlement and tilting of the pile group, axial load and bending moment of each pile at various tunneling stage

EXPERIMENTAL PROGRAM AND SETUP
Determination of Axial Load Bearing Capacity of the pile Group
Findings
This study Reported centrifuge data
Full Text
Published version (Free)

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call