Abstract

Dielectric breakdown accidents have been mainly occurred in the vicinity of service entrance section in underground power transmission systems. One cause among them is due to the excessive component value of sheath located around service entrance of cable. In this paper, as one of the alternative to prevent these accidents, the change of cross bond grounding system and the location change of IJ(Insulation Joint) are suggested. Also, to evaluate effectiveness of this changing system, circulating current and induced voltage of sheath were analyzed in steady and transient state. By comparison of the analytical results for the several possible changing systems, a grounding system and location of IJ which has the smallest sheath component values is proposed. In this paper, analysis to evaluate the proposed system is carried out by EMTP/ATPDraw. It can be used as a valuable operational material to prevent accident of the service entrance section in underground power transmission system.

Full Text
Published version (Free)

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call