It is critical to select the appropriate type of tower cranes for the construction of super tall buildings. However the selection is often made based on subjective personal experiences due to the lack of historical and analytical data. As a result, planning mistakes and efficiency errors sometimes occur. This research is to develop a system of hoisting analysis for appropriate tower crane selection and to provide a flexible statistical model based on the Burj Dubai project. In addition, this system hassupporting functions that can estimate the target construction period per floor, and a decision-making construction period computation method which is based on the characteristic of the selected tower cranes.