Standard Work (SW) focuses on reducing variability and waste based on three conceptual elements: takt-time, work sequence, and work-in-process. Considering the importance of SW implementation in the Construction Industry, there is a need for adapting the conceptual elements due to differences between the production systems. This paper discusses the singularities of SW concepts adaptation in construction processes and proposes four implementation rules. A participatory case study was conducted aimed at the implementing SW in the construction of the reinforced concrete structure of a 26-floor residential building developed by a Brazilian construction company. This process is characterized by long cycle time, a great number of interrelated operations performed by workers with specialized skills who traditionally have autonomy in organizing their work. The singularities refer to the adaptation of the conceptual elements to the context investigated and resulted in four rules to implement SW in the construction industry: (a) define daily work packages as a control parameter due to the long takt- time; (b) focus the specifications of standard work sequences on the team, allowing space for autonomous decisions; (c) establish batches’ size prioritising the sharing of resources between work packages; and (d) define specifications for transporting and storing resources since there are constant modifications of the workstations.
Highlights
The building construction process is characterized by a high level of variability, which negatively impacts its performance in terms of time and cost (Cruz et al, 2018)
5.1 Analysis stage From the analysis of project documents, it was observed that each floor of the reinforced concrete structure was executed in two stages, named Phases A and B (Figure 3)
According to the master plan, the cycle time for each concrete structure floor was defined as ten days
Summary
The building construction process is characterized by a high level of variability, which negatively impacts its performance in terms of time and cost (Cruz et al, 2018). What stands out are the fluctuations in production rates due to the time it takes to prepare and mobilize the workforce, the irregular distribution of the workforce between jobs, difficulties in making resources available in the various workplaces of the building, and the recurrent rework (Brodestkaia and Sacks, 2007); (Vrijhoef, 2016). These difficulties have prompted the Construction Industry to seek concepts and management practices in Manufacturing aimed at the stability of production. Standardization in one of the most important principles in the Toyota Production System (TPS) and it has received the attention of the Construction Industry due to its benefits which promote process stability
Talk to us
Join us for a 30 min session where you can share your feedback and ask us any queries you have
Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.