On January 30, 2012 an auxiliary component of Byron Unit 2 was tripped on bus under voltage. The cause of the event was the failure of the C-phase insulator track for the Un it 2 station auxiliary transformer(SAT) revenue metering transformer. In addition to this event, other events have occurred at other plants resulting in an open-phase condition.(1) Therefore, Nuclear Regulatory Commission(NRC) has requested tha t not only nuclear power plant(NPP) operating company but also its Design Certification(DC) applicant have to prepare open-phase detecting system in their operating plants and design document. In this paper, various open-phase conditions are simulated in NPP using Electromagnetic Transient Program(EMTP) and Atpdraw, and open-phase condition detecting system is proposed for Main Transformer(MT), Unit Auxiliary Transformer(UAT) and SAT connected power line in NPP.

Full Text
Paper version not known

Talk to us

Join us for a 30 min session where you can share your feedback and ask us any queries you have

Schedule a call

Disclaimer: All third-party content on this website/platform is and will remain the property of their respective owners and is provided on "as is" basis without any warranties, express or implied. Use of third-party content does not indicate any affiliation, sponsorship with or endorsement by them. Any references to third-party content is to identify the corresponding services and shall be considered fair use under The CopyrightLaw.